Project Labor Hours Status Report

Use the Project Labor Hours Status report to monitor and manage labor hours at the resource level for existing projects.

To provide the most up-to-date picture, the report includes all unposted timesheet hours from Deltek Time Collection.

For each resource, the report displays the following:

  • Inception-to-date (ITD) actual hours through the period preceding the current period in Costpoint Planning

  • Unposted hours

  • Actual hours for the current period in Costpoint Planning (<current period end date> Actuals column)

  • Budget hours for the current fiscal period in Costpoint Planning (<current period end date> Forecast column)

  • Estimate-at-completion (EAC) hours

  • Hours spent to date (ITD actual hours + Unposted hours + Current period actual hours)

  • Hours remaining (EAC hours – Hours spent to date)

The report displays subtotals for each project level and totals for the report as a whole.