Project Information Subtask
Use the Project Information subtask to establish crew, project, and foreman information
Use this subtask as part of your initial setup.
Table Window
Field | Description |
---|---|
Crew |
Enter, or click
|
Crew Name |
The crew name displays when you enter the crew ID. |
Crew Chief |
The crew chief ID displays from the main screen when you enter the crew ID, but you can change it if necessary. This is a required field. |
Crew Chief Name |
The crew chief name displays when the crew chief ID is entered. |
Project |
Enter, or click
|
Project Name |
The project name displays from the main screen when you enter the project ID. |
Apply to Project's Lower Level |
Select the check box in this column to have the fringe cost applied to the project's lower levels. If you do not select this check box, the fringe cost is applied only at the top level. |
W/H State |
Enter, or click
|
W/H Locality |
Enter, or click
|
Certified Payroll |
Select this check box if this project is an established certified payroll. |
Foreman |
Enter, or click
|
Foreman Name |
The foreman name defaults into this field when you enter the foreman ID. |