Current Budget vs. Final Version

This section describes the differences in the Final Version and Current Budget Flag Y/N columns in the Project Status Details table in Business Intelligence.

Only one version of a committed BUD/EAC can be designated as the final in the Planning module in Costpoint.

Final Version

The final version column reflects the final committed EAC and the final committed budget (BUD) version for a project in the Planning module (i.e. the final BUD and EAC).

Current Budget Flag

The Current Budget Flag (Y/N) column indicates the final version of the committed Budget unless there is an estimate at completion (EAC) defined for the project. If there is an EAC, the Current Budget Flag indicates the final version of the committed EAC (i.e. the final BUD or EAC).