Contents of the Manage Project Level Mapping Screen
Use the fields and options to configure the Manage Project Level Mapping screen.
Identification
Field | Description |
---|---|
Project |
Enter, or click to select, a top-level Costpoint project ID you want to map. |
Name |
This field displays the descriptive name of this project ID. You can click in this field to select the project you want to map, instead of using the Project field. |
Levels |
This field displays the total number of project levels defined for this project ID. |
Populate Levels |
Click this button to load the levels of the selected project in the Project Levels table. |
Project Levels
Use this table to define the number of levels of the Costpoint project you want to transfer to GovWin CRM and how those levels are mapped to the WBS1, WBS2, and WBS3 structures.
Field | Description |
---|---|
Level |
This field displays the Costpoint project level currently being mapped. This value is automatically numbered as new lines are created up to the maximum number of levels for this project ID. |
Length |
This field displays the length of the level being mapped. |
Level Description |
This field displays the description of the level being mapped. |
WBS |
Use this field to enter a work breakdown structure (WBS) number of 1, 2, or 3. |