Contents of the View Summary Part Availability Screen

Use the fields and options to configure the View Summary Part Availability screen.

Contents

Field Description
Part

Use this field to enter, or use to select, the part number for which you would like to view supply/demand information.

Rev

Use this field to enter, or use to select, the revision of the part number for which you would like to view supply/demand information. The description for the part/rev combination displays on the adjacent unlabeled field.

Inventory Project Selection

Use this group box to specify inventory projects that you want to include in this inquiry.

Field Description
Include Common Inventory Projects

Select this check box to include common inventory supply/demand in the results.

Project Selection Option

Use this drop-down list to select the project-grouping option to define what inventory projects you want to view. The available options are:

  • All Projects: Select this option to include inventory supply and demand for all projects.
  • Netting Group: Select this option to include all supply and demand for inventory projects having the same netting group as the one specified in the Netting Group field. If you selected the Include Common Inventory Projects check box, the supply and demand for projects that have been specified as common inventory are also included, even though they may not have the same netting group.
  • Project Planning Group: Depending upon whether the part is common-stock or not, this includes all supply and demand for inventory projects that are within the same project-planning group as the project specified in the Project field. (See the Configure Material Requirements Planning Settings screen.) If the Include Common Inventory Projects check box is selected, the supply and demand for projects that have been specified as common inventory are also included, even though they may not otherwise meet the project selection criteria.
  • Single Project: Select this option to include all supply and demand for the inventory project specified in the Project field. If you selected the Include Common Inventory Projects check box, the supply and demand for projects that have been specified as common inventory are also included.
  • Top-Level Project: Select this option to include all supply and demand for inventory projects that share the same top-level project as the project specified in the Project field. If you selected the Include Common Inventory Projects check box, the supply and demand for projects that have been specified as common inventory are also included, even though they may not have the same top-level project.
Project

Use this field to enter, or use to select, the inventory project for which you would like to view supply/demand information.

Netting Group

Use this field to enter, or use to select, the inventory netting group for which you would like to view supply/demand information.

Date Cutoff

Use this field to enter, or use to select, the last date for which you would like to view supply/demand information.

Warehouse

Use this field to enter, or use to select, the warehouse for which you would like to view supply/demand information. This field is available only if you selected the Plan Warehouse Separately check box in the Corporate Settings block of the Configure Material Requirements Planning Settings screen.

On Hand Quantity

This field displays the total quantities in on hand locations for the selected part within the specified projects and warehouse.

U/M

This field displays the inventory unit of measure for the part/revision.

Other Inventory  Quantity

This field displays the total quantities in shipping, inspection, and reinspection locations for the selected part within the specified projects and warehouse. If you selected the Incl MRB as Available Inventory check box on the Configure Production Control Settings screen in Costpoint Production Control, such location types are also included.

Header Subtask

Subtask Description
Part Detail Select this button to open the Part Detail subtask and view part/project information for the part on the line selected in the main screen.

Weekly/Monthly Summary

This table window displays the weekly/monthly summary for the selected part/rev combination.

Field Description
Period End Date

This field displays the end date of the period. Weekly time buckets are used and supply/demand information within that week will be combined and displayed as a sum. The first end-of-period row shows all supply/demand that is past due as of the current date. The second row's period end date depends on which day is selected as the Ending Day of Production Week on the Configure MRP Report Print Options screen. End dates for subsequent rows will be in weekly increments. Depending on the values set in the Summary Report/Inquiry Weekly field in the Configure MRP Report Print Options screen, the time buckets displayed will change from weekly to monthly, and will continue until the value set in Summary Report/Inquiry Monthly is reached, or until the Date Cutoff is reached. Any additional supply/demand beyond this limit is summarized into a single future bucket.

Reserved Quantity

This field displays the sum of all the demand quantities (in inventory unit of measure) within the period for the row.

Supply Quantity

This field displays the sum of all the supplies (in inventory unit of measure) within the period for the row.

Supply Yield Quantity

This field displays the supply quantity adjusted for the part's yield factor (Supply Yield Quantity = Supply Quantity x Yield %). This field is displayed if you have selected the Incl Scrap/Yield % in Planning Process check box in the Configure Production Control Settings screen in Costpoint Production Control.

Planned Order Quantity

This field displays the sum of all the planned orders within the date range of the period for the row.

Planned Reserved Quatity

This field displays the sum of all the demands created as a result of planned orders, and which are within the date range of the period for the row.

Projected Available Quantity

This field displays the total available quantity after accounting for additional supply and demand.

For the first row in the table, Projected Avail Qty = On Hand Qty + Other Inv Qty + Supply Quantity - Demand Quantity (first row).

In subsequent rows, Projected Avail Qty = Projected Avail Qty (previous row) + Supply Quantity - Demand Quantity (current row).

Note:

Supply Yield Quantity is used in the calculations instead of Supply Quantity if you selected the Incl Scrap/Yield % in Planning Process check box in the Configure Production Control Settings screen in Costpoint Production Control.

Weekly/Monthly Summary Subtasks

Subtask Description
Projects Select this button to open the Projects subtask and view project and inventory abbreviation information based on project selection criteria.
Warehouse Inventory Select this button to open the Warehouse Inventory subtask and view current inventory information by warehouse for the selected part.
Inventory Details Select this button to open the Inventory Details subtask and view current inventory information for the selected part across all warehouses.
Supply Select this button to open the Supply subtask and view details about the supplies that make up the supply quantity.
Demand Select this button to open the Demand subtask and view details about the demands that make up the demand quantity.
Substitutes Select this button to open the Substitutes subtask and view current inventory information for substitute parts.
ECNs Select this button to open the ECNs subtask and view information on Engineering Change Notices for the part.